How to Apply for an Unlicensed Solar Power Plant in Türkiye: 2026 Guide
RegulationPublished: · Updated: · 9 min read

How to Apply for an Unlicensed Solar Power Plant in Türkiye: 2026 Guide

Short answer

An unlicensed solar plant in Türkiye starts with a connection application to the local distribution company; a positive result brings a call letter. The design must then be approved within one year of the call letter, after which the connection agreement is signed, the plant is built and accepted. Since the 2 April 2026 amendment, non-residential plants are netted hourly and annual output is capped at twice the linked consumption.

Key facts

Key facts
ItemValueSource
Statutory capacity limit for unlicensed renewable plantsUp to 1 MW; the President may raise this ceiling up to 5 times per sourceElectricity Market Law No. 6446, Art. 14(1)(b) and 14(2)Checked:
Industrial plants, municipalities, agricultural irrigationTwice the contracted power in the connection agreement; other persons up to the contracted powerLaw No. 6446, Art. 14(1)(g)Checked:
Annual output capTwice the linked consumption facilities' annual total; no payment for surplus above the cap (residential excluded; plants with call letters from 12 May 2019)Unlicensed Electricity Generation Regulation Art. 26(17) (Official Gazette 02.04.2026/33212, Art. 13)Checked:
Netting periodHourly; monthly for plants linked to residential subscriptions. In force: 1 May 2026Regulation Art. 26(1) and 26(20) (OG 33212, Art. 13); OG 33212, Art. 26Checked:
Design approval period1 year from service of the call letter; if documents are not submitted in time, the right to sign a connection agreement is lostRegulation Art. 17(1) and 17(4) (Official Gazette 14.05.2024/32546, Art. 4)Checked:
Integrated storageUp to the plant's electrical capacity; no payment for energy exported from storageRegulation Additional Art. 3(1)-(2) (OG 33212, Art. 23)Checked:

How Do You Apply for an Unlicensed Solar Power Plant in Türkiye?

You apply by submitting a connection application to the electricity distribution company (EDAŞ) that serves your region. Which plants are exempt from the obligation to obtain a license and set up a company is defined in Article 14 of Electricity Market Law No. 6446, based on the plant type and the contracted power in the connection agreement (details below). In short, the process has five steps: (1) connection application, (2) a call letter if the application is approved, (3) approval of the generation facility design, (4) signing the connection agreement, and (5) construction, acceptance and commissioning.

The main advantage of the unlicensed route is that the process runs through the distribution company, without a generation license from EMRA or a dedicated project company. Being unlicensed does not, however, mean being exempt from the Environmental Impact Assessment (EIA, known locally as ÇED): Article 19 of the regulation requires EIA, zoning and other permits to be obtained within the set period, and whether a solar plant falls under the EIA Regulation depends on its project area, with rooftop and facade systems excluded. Plants connected at the same metering point as the applicant's own consumption receive priority, and their output is offset against that consumption under the netting principle. A well-prepared application file can shorten the process by months, while missing or incorrect documents can lead to rejection or a lower position in the queue.

The sections below explain the regulatory framework, the installed capacity limits, the step-by-step application flow, the required documents and the hourly netting, annual output cap and storage rules introduced by the 2 April 2026 amendment, all from an engineering contractor's perspective. For international investors and EPC contractors, we also clarify the Turkish terms you will encounter along the way.

What Is the Difference Between Unlicensed and Licensed Solar Plants in Türkiye?

The difference comes down to the regulatory route: plants listed in Article 14 of Electricity Market Law No. 6446, typically built mainly to meet the owner's own electricity consumption, can be built without a license and are processed by the distribution company, while other plants need a generation license from the Energy Market Regulatory Authority (EMRA, known in Turkish as EPDK). Under the unlicensed model there is no obligation to obtain an EMRA generation license or to set up a dedicated project company; the process runs through the distribution company and the regulatory path is far simpler.

Plants outside the unlicensed scope must obtain a generation license from EMRA, a route that involves a pre-license phase and additional administrative obligations. Investment size and administrative workload rise considerably as a result. This guide focuses on the unlicensed model, the most common route for SMEs, industrial plants, companies located in Organized Industrial Zones (OIZs, known in Turkish as OSB) and businesses that want to put their rooftops to work.

The core logic of the unlicensed model is self-consumption: the energy you generate is netted against the energy you draw from the grid, which noticeably lowers your electricity bills. For manufacturers that want to stabilize their energy costs, an unlicensed SPP is therefore a strategic investment in cost control.

What is the installed capacity limit, and which plants can be built without a license?

The basic statutory threshold is a renewable generation plant with an installed capacity of up to 1 MW (Law No. 6446, Art. 14(1)(b)); the President is authorized to raise this ceiling up to five times per source (Art. 14(2)). Municipalities and their affiliates, industrial plants and agricultural irrigation facilities may build renewable plants of up to twice the contracted power in their connection agreement, and other persons up to the contracted power itself (Art. 14(1)(g)). Because these limits determine which regulatory track the application follows, they should be fixed together with the presidential decision in force and the facility's contracted power at the first step of a solar feasibility study.

Rooftop solar installations are the most practical application of the unlicensed model, since they use existing building and factory roofs, require no additional land and are usually located close to the point of consumption. For ground-mounted plants, site suitability, zoning status and available grid connection capacity become the key technical criteria, and they are assessed for the specific site during solar plant design.

Applications are prioritized based on criteria such as whether generation and consumption share the same metering point, annual consumption volume and contracted power. For this reason, plant capacity should be sized to the facility's actual consumption profile. An oversized system puts the application at a disadvantage in the queue and, once it runs into the netting rules, fails to deliver the expected return.

What Are the Steps of the Unlicensed Solar Application Process?

The application is filed with the regional distribution company and moves through five steps: connection application, call letter, design approval, connection agreement, then installation, provisional acceptance and commissioning. 1) Connection application: The process starts with a connection application submitted through the distribution company's electronic application system. Plant capacity, location and consumption data are declared at this stage, and the application is assessed against the technical capacity of the grid.

2) Call letter: If the application is approved, the distribution company issues a call letter (çağrı mektubu). For unlicensed projects, obtaining the call letter is the first critical milestone; no subsequent step can begin without it. If the outcome is negative, the reasons are stated and the applicant can revise the file or submit a new application.

3) Design approval: Once the call letter is served, the applicant has one year to have the generation facility design and, if applicable, the connection line design approved by the Ministry of Energy and Natural Resources or an institution or entity it authorizes (Regulation Art. 17(1), as amended on 14 May 2024). If the documents are not submitted to the network operator within that period, the right to sign a connection agreement is lost. We prepare this file as part of our project approval and permit consultancy.

4) Connection agreement: With the approved design and a complete file, the connection agreement is signed between the individual or legal entity and the distribution company. This agreement defines the point and the conditions under which the plant will connect to the grid. From the signing date, the EIA, zoning and other permits and the acceptance procedures must be completed within one year for plants that use the network operator's distribution transformer and within two years for solar plants that do not (Art. 19(1)).

5) Installation, provisional acceptance and commissioning: The plant is then built in line with the approved design, for example as a turnkey solar installation. When installation is complete, a 'Ready for Provisional Acceptance' report is issued, acceptance procedures are carried out and the plant is commissioned.

Which Documents Are Required for an Unlicensed Solar Application?

The core file consists of equipment datasheets with conformity certificates, a site suitability document and copies of the approved designs, although exact requirements differ slightly between distribution companies. In practice this means datasheets for the PV modules, cables and inverters together with documents proving their compliance with standards and certification bodies such as TSE (the Turkish Standards Institution), IEC and TÜV; a site suitability document issued by the relevant municipality or the Ministry of Environment, Urbanization and Climate Change; and copies of the approved generation facility design and, if applicable, the connection line design.

In addition, distribution companies request an authorization document for the individual or legal entity, a certified signature circular or signature declaration, and the applicant's identity or company details. Subscription data and contracted power for the consuming facility also matter in the assessment, because the plant capacity is evaluated against these figures.

The quality of the technical file directly affects how quickly an application is accepted. Single-line diagrams, protection coordination, and grounding and cabling calculations that are consistent and prepared in line with the applicable standards eliminate resubmissions caused by missing datasheets or conformity documents. A file that has passed an engineering review shortens approval times and prevents surprise revisions during commissioning.

What did the 2 April 2026 amendment change for netting and output limits?

Netting for unlicensed generation was calculated monthly for many years, and 2026 brought a major change. Its legal basis is not an EMRA Board decision but the amendment to the Unlicensed Electricity Generation Regulation published in Official Gazette No. 33212 on 2 April 2026. Under it, plants based on renewable sources that became entitled to a call letter from 12 May 2019 onwards are netted hourly, while plants linked to residential subscriptions continue to be netted monthly (Art. 26(1) and 26(20)). The relevant provisions entered into force on 1 May 2026. In practice, the value of your generation is now matched against your consumption in the same hour in which it was produced.

This makes designing the system around the facility's consumption profile more critical than ever. Industrial and commercial businesses that generate and consume during daytime hours benefit from hourly netting, while facilities whose generation and consumption hours do not overlap need to choose capacity carefully and, where necessary, consider options such as battery energy storage. Residential subscribers are excluded from this rule and continue to be assessed under monthly netting and the protections for individual generation.

While the technical infrastructure for the rule is being phased in, an hourly analysis of your consumption data before applying is decisive for a sound investment decision. Because regulations and implementing procedures are updated from time to time, applicants should rely on the latest announcements from their regional distribution company and EMRA at the time of application.

The same amendment also capped annual output: for plants that received a call letter from 12 May 2019 onwards, generation in a calendar year may not exceed twice the annual total consumption of the linked consumption facilities. The cap is generally calculated from pre-netting consumption in the previous calendar year; surplus exported above the cap after netting is not paid for and counts as a free contribution to YEKDEM, the renewable energy support mechanism. The rule does not apply to plants linked to residential subscribers (Art. 26(17)). We discuss the investment impact in our article on solar payback under hourly netting.

The amendment also regulates storage: an integrated storage unit can be added to an unlicensed plant up to the plant's electrical capacity. No payment is made for energy exported from storage, and if that amount cannot be determined, no payment is made for any of the surplus (Additional Art. 3). We explain the architecture options in our article on adding storage to a solar plant.

What Are the Most Common Application Mistakes, and How Does Miratek Help?

The most common problems in unlicensed solar applications are missing or non-compliant conformity documents, incorrectly sized plant capacity, designs that do not match the consumption profile, inconsistencies in single-line diagrams and protection coordination, and failing to obtain the site suitability document on time. These mistakes lead to rejection, longer timelines or delayed commissioning.

At Miratek Elektrik, our SPP Design and SPP Installation and Commissioning services cover the entire process from feasibility to turnkey delivery: consumption analysis and capacity sizing, preparation of the application file, DC/AC cabling and inverter installation in line with the approved design, grid connection and provisional acceptance. On licensed and unlicensed, rooftop and ground-mounted projects alike, we deliver engineering under our ISO 9001:2015, ISO 14001:2015 and ISO 45001:2018 management systems, in compliance with the applicable IEC standards and the specifications of TEDAŞ (Turkish Electricity Distribution Company).

With our team's 15+ years of field experience, 1,300+ completed projects and 50 MW of installed solar capacity, we manage both the administrative and technical sides of the application through a single point of contact and keep resubmissions to a minimum. We work on projects across Türkiye and act as the local electrical engineering and contracting partner for international investors and EPC contractors. Contact our team to review your consumption profile together before you plan your unlicensed SPP investment.

Frequently Asked Questions

Do you need a license or a company to build an unlicensed solar power plant in Türkiye?+

No. Plants covered by Article 14 of Law No. 6446 (for example renewable plants of up to 1 MW, or industrial plants of up to twice their contracted power) are exempt from the obligation to obtain a license and set up a company. The President may raise the 1 MW ceiling up to five times per source. The process runs through the regional distribution company.

Where do you submit an unlicensed solar power plant application?+

To the electricity distribution company (EDAŞ) serving your region. Check the distribution company's current announcement at the time of application to confirm the submission channel and the required documents.

What is a call letter and why does it matter?+

The call letter (çağrı mektubu) is the document confirming that your connection application has been approved. In unlicensed projects, you cannot move on to design approval or the connection agreement without it.

How long does an unlicensed solar application take?+

It depends on how complete the file is and on available grid capacity. Once the call letter is served, there is one year to have the design approved (Regulation Art. 17(1)). After the connection agreement is signed, permits and acceptance must be completed within one year for plants using the distribution transformer and within two years for solar plants that do not (Art. 19(1)).

Is an EIA report required for an unlicensed solar power plant?+

Unlicensed status alone does not exempt a plant from EIA (ÇED). Since the amendment of 26 June 2025, the EIA Regulation lists solar plants with a project area of 25 hectares or more in Annex 1 (full EIA) and those of 7.5 hectares or more in Annex 2 (screening); rooftop and facade systems are excluded from these items. Article 19(1) of the unlicensed regulation also requires EIA, zoning and other permits to be obtained within the set period.

What did hourly netting change in 2026?+

From 1 May 2026, unlicensed plants that received a call letter after 12 May 2019 and are not linked to residential subscriptions are netted hourly (Official Gazette 02.04.2026/33212). Because generation is matched against consumption in the same hour, sizing the system to the facility's consumption profile has become more critical; the same amendment also caps annual output at twice the linked consumption.

Sources

  1. Regulation Amending the Unlicensed Electricity Generation Regulation (Official Gazette 33212, in Turkish) — Official Gazette / EMRA, (accessed: 2026-10-05)
  2. Electricity Market Law No. 6446 (in Turkish) — Turkish Legislation Information System (accessed: 2026-10-05)
  3. Amendment to the Unlicensed Electricity Generation Regulation (Official Gazette 32546, in Turkish) — Official Gazette / EMRA, (accessed: 2026-10-05)
  4. Amendment to the Environmental Impact Assessment Regulation (Official Gazette 32938, in Turkish) — Official Gazette / Ministry of Environment, Urbanization and Climate Change, (accessed: 2026-10-05)
  5. Unlicensed Electricity Generation Regulation (Official Gazette 30772, in Turkish) — Official Gazette / EMRA, (accessed: 2026-10-05)